Location:

Des Moines, IA

Scope of Work:

Exterior

Contract Value:

$56,350

Date:

August 8th, 2017 – August 12th, 2017

Client:

Hubell Construction

This project consisted of the removal of the existing Ronald McDonald house in Des Moines, IA.

The project had an accelerated schedule as Hubbell Construction had an 11 day build schedule for the new Ronald McDonald House.
Iowa Demolition completed our scope of work one day ahead of schedule giving the contractors performing work behind us a small advantage.

In the end this project was a success for everyone involved.