Abatement | Demolition | Contaminated Soils
Scope of Work: Soil Remediation
Contract Value: $1.2 million Date: Feb 2014 - May 2014 Client: City and County of Denver

Johnson Habitat Remediation

Denver, CO

As part of an overall project to complete improvements at the Johnson Habitat Park, the City and County of Denver selected ESA to perform soil remediation prior to the start of construction. The project involved the removal of approximately 10,000 cubic yards of friable asbestos impacted soil. Once remediation was complete, ESA imported and compacted clean fill for the construction of the new park.